Team report
The work schedule for the first batch
Problem: make 10 swings safely by 29 October. Numbers: TR = 600 000, TC = 452 000, profit 148 000 (37 000 each). Hours: a run is 15 hours (grandpa 7, team 3, work party 5). Executors: lathe and knife — only grandpa; sanding, painting and checking — the team and work-party helpers. Decision: two runs of 5; run 1 on 10–14 October, run 2 on 17–21 October, 22–23 October spare. Angles are checked with a template. Lessons first.