Write the five stages of a project plan in order. Add one sentence for each stage for a program that tells the time of the next school bus.
Requirements, design, implementation, testing, evaluation. Check that each sentence matches its stage, for example ‘Requirements: the program must say the time of the next bus’.
2
Trace the program. The user types 4, then 6, then 9. What does it say?
The total goes 4, 10 and 19, so it says Total: 19.
3
Write a test plan with four tests for the rule ‘a bonus is given for a score of 100 or more’. Include the boundary values.
For example: score 20 (no bonus), 99 (no bonus), 100 (bonus), 101 (bonus). The edge is at 100.
4
Evaluate a friend’s program or your own. Draw a table with each requirement, met or not met and the evidence. Add one improvement idea.
Check that every requirement has a result and evidence from a test, and that the improvement idea is specific.
5
(if you have a computer or tablet) Build the savings jar from this week in Scratch. Run the four tests from the test plan and write down the actual results.
The results should match the expected column: Keep saving, Goal reached!, Keep saving, Keep saving.